In the beginning of 2002, the State Council approved the Letter
of Project Proposal of China's second largest LNG project -Fujian
LNG project, and now the feasibility study report is preparing intensely.
According to the plan, it will start construction in the second
half of 2003, run trial operation in 2006 and commerce operation
at the beginning of 2007. After 3 year, 5 cities' people in Fujian
province can use clean energy.
The project is designed to provide LNG of 5 million t/a, and 2.5
million t/a in the first phase with a total investment of RMB11.98
billion.
On September 26, 2002, China National Offshore Oil Corporation
(CNOOC ) signed a 25-year LNG Sale & Purchasing Agreement with
PERTAMINA on behalf of Tangguh gas field in Jakarta to be upstream
product cooperator. In the agreement, Fujian LNG project is the
second largest following Guandong LNG Project. Fujian LNG receiving
station will be co-invested by CNOOC and Fujian Investment and Development
Company.
From 1990's Fujian province has been considering to import LNG
and cooperating actively with CNOOC to carry out the "Coastal
Districts LNG Layout Study in Southeast China". In November
1997, Fujian provincial government and CNOOC jointly organized the
Fujian LNG project leading group, and with the suggestions from
experts, Xiuyu County in Putian was finalized as the best location
for the project.
On January 3, 2003, preparatory committee of Fujian LNG project
Putian office was established. According to the plan, before June
20, 2003 the feasibility study report should be finished and passed
the experts* final examination, gas station projects be concluded
and reported, the feasibility study report of general project should
be edited and reported to the government on the basis of fixing
the gas market, and the contract should be signed through the business
negotiations.
Fujian LNG project included one receiving station, gas transferring
pipe project and seven gas utilization projects. The storage tank
of 120 000 cubic meters, a dock which can anchor LNG freight of
136 000m3, 340 kilometers gas pipeline (main pipe of 311.9 kilometers
and branch pipe of 28.6 kilometers) will be set up in first phase
construction, and in the second phase another 120 000 cubic meters
storage tank will be built.
At present, the feasibility study report for constructing Huian
(Dun'nan) LNG Power Plant in north of Quanzhou Bay is editing tensely
and is expected to start the construction of the 1.5 million KW
LNG power plant before the end of the year. As for the Jinjiang
LNG power Plant in south Quanzhou Bay is undergoing the feasibility
study editing and location choosing, and the special layout is under
discussion. The construction of 2 LNG power plants mentioned are
included in the Fujian LNG project.
The experimental LNG projects in Guangdong and Fujian show that
China's energy and environment industry is developing towards the
international advanced level and exploring the new methods to solve
the problems between energy and environment.
Sources show that 70% of the LNG in Fujian province is applied
to generate electricity.
|