| Shan-Jing pipeline(from Qingbian to Beijing) is
a key national project as well as a backbone project for the early
stage of ¡°West to East Gas Pipeline ¡± project, being as one up to
top level of construction in China.
Shan-Jing pipeline(from Qingbian to Beijing) is the first long distance
and large diameter gas transmission pipeline with highly automation.
The project initialed in Mar.1996 and completed on Sep.10,1997,
having a total length 918.42 km£¬design pressure 6.4Mpa and an annual
delivery capacity over 13.2 ¡Á108 m3 without boosting. The booster
station (Yushulin gas station)at phase 2 was completed on Nov.10,1999
to increse the capacity to 22 ¡Á108 m3. The booster station ( West
yellow river and Yingxian Stations)at phase 3 was completed on Nov.15,2000
to reach a capacity 33¡Á108 m3.
Shan-Jing thunk pipeline starts from the natural gas purification
plant in Changqing gas field, located in Jingbian county, Shaanxi
province and terminats in the Yamenkou terminal in Shijingshan district,
Beijing, passing through 22 counties in Shaanxi, Shanxi and Hebei
as well as Beijing city. This pipeline crosses three earthquake
zones and passes through three mountain ranges(Luliang, Hengshan
and Taihangshan) and five rivers(Wuding river, Tuwei river, Yaoye
river, yellow river and Yongding river). The whole pipeline passes
through rivers at 230 placess, railways at 21 places and highways
at 131 places. In view of peak shaving, Dazhangtuo underground gas
storage and its auxiliary 118.5 km pipeline was completed on Jan.6,2000,
providing a peak shaving capacity 500 ¡Á104m3 /d and an annual net
peak shaving 6 ¡Á108m3.
For all of Shan-Jing pipeline engineering, accepted internationally
advanced standards were adopted. The pipeline was designed by the
Pipeline Design Institute jointly with foreign company and constructed
by NO.1,2 & 3 pipeline construction companies and the oilfield
construction companies from Daqing, Changqing and Sichuan.
The construction of Shan-U pipeline(from Shanshan to Urumchi)started
on 26th Sept.1995 and completed on 30th Sept.1996. It was operated
formally on March 10,1997. With a total length of 301.6km, the pipeline
passes through rivers at 6 places, railways at 6 places and roads
at 79 places.
Shan-U pipeline is a gas transmission pipeline with highly automation.
It was the first application of epoxy powdered coating for corrosion
prevention of the pipeline as well as the first time in china to
lay the optical communication cable in the same ditch. The pipeline
has an overall length of 310.78km.
Shan-U pipeline is also a large onshore project, which was organized
and constructed for the first time up to the international practice.
For the project, supervision system ( with a supervision scope:
the whole process, including basic design, detail design, construction,
commissioning, acceptance inspection and start-up) and an independent
quality supervision system were introduced. A lump-sum contracting
was used for the engineering, also known as ¡°Turn key project¡± as
a common practice for international engineering.
There are both oil and gas reservoirs in Tarim oilfield, Xinjiang.
Particularly, the as reservoirs have abundant resources with great
prospecting for development. In 1996, the proven OGIP was accumulated
to 305.23 ¡Á108m3. The construction of gas transmission pipeline
initialed in the same year. By the end of 20 century, the proven
OGIP was up to over 5000¡Á108m3. The completed gas transmission pipelines
include Tar-Lun pipeline, Lun-Ku pipeline. The trunk pipeline for
¡°West to east gas transmission¡± starts also here to Shanghai.
The construction of pipeline from Tazhong to Lunnan (Ta-Lun) began
on the first day of Jul.1995 and completed on Aug.16,1996 with a
total length 302.15km. It is the first gas transmission pipeline
in China, passing through desert and laid in the same ditch along
with Tar-Lun oil transportation pipeline and optical communication
cable.
|